< img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=486374608200848&ev=PageView&noscript=1" />

Nirvana

Hira Registration no. : HIRA/P/SOU/2019/000318
near Southern Bypass, Very close to E.M Bypass

62 Lacs onwards

Project Images

Nirvana Aerial View
Nirvana front View
Nirvana Evening View
Nirvana Banquet Lawn View
Nirvana Barbecue Zone View
Nirvana Gate Evening View
Nirvana Gate Morning View
Nirvana Club Roof top Solar Panal
Nirvana Villa Day View

Construction Update

Cluster-13 (row house no. 216-220) foundation works in progress. (Pile cap & tie beam work in progress) 01.03.2021
Cluster-14 foundation/ground floor slab casting, 1st floor slab casting and Roof slab casting of row house no. of 199 to 210 has been completed. Roof work and plastering work in progress. 01.03.2021
Cluster-15 foundation/ground floor slab casting, 1st floor slab casting and Roof slab casting of row house no. of 211 to 215 has been completed. Roof work and plastering work in progress. 01.03.2021
Cluster-16 foundation/ ground floor slab casting, 1st floor slab casting and Roof slab of 187 to 191 has been completed. Roof work and plastering work in progress. 01.03.2021
Cluster-17 foundation/ground floor slab casting has been completed. 1st floor slab of 178 to 181 has been completed. Roof slab completed. Brickwork in progress. 01.03.2021
Cluster-19 foundation work and 1st floor slab casting of unit no. 163 to 167 has been completed. Brickwork (up to 2nd floor) in progress. 01.03.2021
Cluster-20 foundation has been completed (except row house no. 177). 1st floor slab casting of 168 to 175 has been completed. Also roof slab casting of 168 to 174 is completed. Above roof work in progress. 01.03.2021
Cluster-22 (row house no. 148-152) foundation work has been completed and Brickwork up to 1st floor in progress. 01.03.2021
Cluster-23 (row house no. 138-147) foundation has been completed (except row house no. 138 & 139). 1st floor slab casting of 140 to 147 has been completed. 2nd floor brickwork in progress. 01.03.2021
Cluster-26 foundation/ground floor slab casting, 1st floor slab casting, Roof slab casting and Brick work of unit no. of 122 to 127 has been completed. Foundation work of unit no. 120 & 121 is completed. 01.03.2021
Cluster-27 foundation/ground floor slab casting, 1st floor slab casting, roof slab casting and brick work of unit no. 107 to 111 has been completed. Foundation & brickwork of unit no. 112 to 114 is progress. 01.03.2021
Cluster-28 foundation has been completed (except 136 & 137) and 1st floor slab casting of unit no. 128 to 134 has been completed. Also roof slab casting of 128 to 130 completed. 1st & 2nd floor brickwork in progress. 01.03.2021
Cluster-29 foundation work and 1st floor slab casting of row house no. of 101 to 106 has been completed. Brickwork (up to 2nd floor) in progress. 01.03.2021
Cluster-33 foundation/ground floor slab casting has been completed and 1st floor slab casting of row house no. Of 71 to 81 has been completed. Brickwork (up to 1st & 2nd floor) in progress. 01.03.2021
Cluster-34 foundation/ground floor slab casting, 1st floor slab casting, roof slab casting and brick work of unit no. Of 53 to 64 has been completed. Finishing work in progress. 01.03.2021
Cluster-35 (row house no. 82-83) foundation has been completed. Brickwork (up to 1st floor) in progress. 01.03.2021
Cluster-36 (row house no. 50-52) foundation has been completed. Brickwork (up to 1st floor) in progress. 01.03.2021
Cluster-39 foundation work has been completed and 1st floor slab casting of row house no. Of 1 to 11 has been completed. Brickwork (up to 2nd floor) in progress. 01.03.2021

Project Video

 
Nirvana
 

Why you should choose this property ?

  • Skylight Roof for more natural light inside.

  • 96% to 100% light in each house.

  • Less than apartment price with ZERO super built up price.

  • Car parking attached to your doorstep.

  • Optimised window to carpet area ratio for more fresh air.