Construction Update

Cluster-13 (Row House No. 216-220) foundation work in progress. ( pile cap & tie beam work in progress) (08.01.2021)
Cluster-14 (Row House No. 199-210) foundation/ground floor slab casting, 1st floor slab casting and roof slab casting of row house no. Of 199 to 210 has been completed. Above roof work in progress (08.01.2021)
Cluster-15 (Row House No. 211-215) foundation/ground floor slab casting, 1st floor slab casting and roof slab casting of row house no. Of 211 to 215 has been completed. Above roof work in progress (08.01.2021)
Cluster-16 (Row House No. 187-191) foundation/ ground floor slab casting, 1st floor slab casting and roof slab of 187 to 191 has been completed. Above roof work and plastering work in progress (08.01.2021)
Cluster-17 (Row House No. 178-186) foundation/ground floor slab casting has been completed. 1st floor slab of 178 to 181 has been completed. Brick work in progress (08.01.2021)
Cluster-19 (Row House No. 163-167) foundation work has been completed and brickwork in progress (08.01.2021)
Cluster-20 (Row House No. 168-177) foundation has been completed (except row house no. 177). 1st floor slab casting of 168 to 175 has been completed. Also roof slab casting of 168 & 169 is completed. 1st floor brickwork in progress (08.01.2021)
Cluster-22 (ROW HOUSE NO. 148-152) foundation work has been completed and brickwork in progress (08.01.2021)
Cluster-23 (Row House No. 138-147) foundation has been completed (except row house no. 138 & 139). 1st floor slab casting of 141 to 147 has been completed. 1st floor brickwork in progress (08.01.2021)
Cluster-27 (Row House No. 107-111) foundation/ground floor slab casting, 1st floor slab casting, roof slab casting and brick work of unit no. 107 to 111 has been completed. Plastering work in progress (08.01.2021)
Cluster-28 (Row House No. 128-137) foundation has been completed (except 136 & 137) and 1st floor slab casting of row house no. 128 to 134 has been completed. Also roof slab casting of 128 to 130 completed. 1st floor brickwork in progress (08.01.2021)
Cluster-29 (Row House No. 101-106) foundation work in progress and 1st floor slab casting of row house no. Of 103 to 106 has been completed. Brick work (up to 1st floor) in progress (08.01.2021)
Cluster-33 (Row House No. 71-81) foundation/ground floor slab casting has been completed and 1st floor slab casting of row house no. Of 71 to 81 has been completed. Brickwork (up to 1st floor) in progress (08.01.2021)
ClusteR-34 (Row House No. 53-64) foundation/ground floor slab casting, 1st floor slab casting, roof slab casting and brick work of unit no. Of 53 to 64 has been completed. Plastering work in progress (08.01.2021)
Cluster-35 (Row House No. 82-83) foundation has been completed. Brickwork (up to 1st floor) in progress (08.01.2021)
Cluster-36 (Row House No. 50-52) foundation has been completed. Brickwork (up to 1st floor) in progress (08.01.2021)
Cluster-39 (Row House No. 1-11) foundation work has been completed and 1st floor slab casting of row house no. Of 1 to 8 has been completed. Brickwork (up to 1st floor) in progress (08.01.2021)

Project Video

Nirvana

Why you should choose this property ?

  • Skylight Roof for more natural light inside.

  • 96% to 100% light in each house.

  • Less than apartment price with ZERO super built up price.

  • Car parking attached to your doorstep.

  • Optimised window to carpet area ratio for more fresh air.